Engineering & Construction
Engineering and Construction
A wharf in Honiara starts as a bidding document written in Manila or Tōkyō. The contractor may come from Beijing and the supervising engineer from Brisbane. English is the language of the contract. Pijin is the language of the site. The parties exchange specifications and method statements from the first notice to the last defect. Huri Translations works on those papers and on the inductions and handover manuals read by the people who build and run the asset. An engineer writes of loads and tolerances. A foreman names the load and the signal to stop.
A Wharf, from Tender to Handover
A ministry of infrastructure publishes bidding documents for a wharf. The package has a bill of quantities and technical specifications. Bidders price the piles, the deck and the fenders against the drawings. An evaluation committee scores the bids and the funder checks the award.
The winning contractor submits method statements and a programme of works before mobilising. The engineer reviews them against the specification. Wharf users hear the traffic and safety arrangements at a public briefing in Honiara. Our Solomon Islands Pijin Translation Services translate the traffic plan and the safety notices.
During construction the engineer gives site instructions and the contractor answers with requests for information. Inspection and test plans record concrete pours and pile driving. A foreman explains a hold point to a crew before the pour. The record of that explanation belongs in the quality file.
At handover the contractor delivers as-built drawings and a maintenance manual. Crane operators and fitters at the port read the manual in sections. Port staff in Port Vila work in Bislama on a wharf built with Japanese finance. Our Bislama Translation Services translate maintenance schedules and operator checklists.
FIDIC Sub-Clause 1.4
Sub-Clause 1.4 of the 2017 FIDIC Conditions of Contract for Construction fixes the governing law and the ruling language of the contract. It also fixes the language of notices and correspondence. A version in a second language has standing only as a working aid. The ruling text prevails in a dispute.
Sub-Clause 20.2.1 gives a contractor 28 days to give a Notice of Claim after becoming aware of the event. State-owned contractors from Beijing build roads and wharves across the region. A notice written first in Chinese at head office has to be given in English by day 28. Our Simplified Chinese Translation Services translate notices and engineer’s determinations in both directions.
Japanese grant aid has its own conditions and a Japanese consultant. The consultant in Tōkyō writes design reports in Japanese first. The client ministry approves drawings from an English set. Our Japanese Translation Services translate design reports and inspection records for the ministry.
Employer, Engineer, Contractor, Landowner
The employer is a ministry or a state-owned utility. A consulting firm appointed under the contract is the engineer. The contractor gives its notices to the engineer and takes its instructions from the same office. A fourth party stands outside the contract and owns the ground.
The contractor addresses its workforce through site inductions and toolbox talks. A site in Port Moresby works in Tok Pisin and English. A permit-to-work form names the hazard and the isolation applied. Our Tok Pisin Translation Services translate induction scripts and permit forms.
A landowning unit in Fiji gives consent to works on native land through the iTaukei Land Trust Board in Suva. The unit signs a land access agreement and a compensation schedule before the survey. Our Fijian Translation Services translate consent forms and compensation schedules. A reviewer checks plot names against the survey plan.
Guam, 2016: H-2B Petitions Denied
Contractors on Guam staff large projects with skilled workers recruited in Manila on H-2B visas. USCIS approved about 95% of Guam petitions from 1995 to 2015. In the 2016 calendar year the approval rate for repeat petitioners fell to 0.3%, by the plaintiffs’ count.
The Guam Contractors Association and 11 other plaintiffs sued on 4 October 2016. The District Court of Guam granted a preliminary injunction on 24 January 2018. Section 1049 of the NDAA for fiscal year 2018 then allowed up to 4,000 H-2B workers a year on Guam for military realignment work. The exemption applied from 11 April 2018.
A petition file holds a temporary labour certification and the worker contracts. The Guam Department of Labor inspects the housing and the pay records. A welder or a mason signs a contract in English and reads the house rules in Tagalog. Our Tagalog Translation Services translate contracts and housing rules for employers in Hagåtña.
A Water Supply, from Design to Handover
South Tarawa draws its water from a thin freshwater lens under the atoll. The South Tarawa Water Supply Project adds desalination and a new pipe network. Among its funders are the Asian Development Bank and the Green Climate Fund. The design consultant writes a hydraulic model report and tender drawings.
The Public Utilities Board in Tarawa comments on the design. Landowners along the pipe route receive a notice of works and a plan of the trench. Our Gilbertese Translation Services translate consultation notices and the plan legends. A surveyor reads the plot names back to the families at the meeting.
The contractor disinfects and pressure-tests the mains before commissioning. The laboratory reports water quality against the WHO Guidelines for Drinking-water Quality. A commissioning certificate lists the tests passed and the valves left open. The utility takes over the network with a set of standing procedures.
On an outer atoll of the Marshall Islands the system is a rainwater tank and a tap stand. A tank committee receives the keys and a maintenance sheet. Our Marshallese Translation Services write the maintenance sheet for the committee and the ministry in Majuro.
What Breaks in a Drawing File
AutoCAD draws text with a TrueType font or with an older SHX shape font. The standard SHX fonts hold a limited Latin set. A macron vowel in a street name prints as a question mark in the title block. Swapping to a TrueType font changes the text width across the sheet.
A building model exchanged as an IFC file follows ISO 10303-21. The file is plain ASCII. It writes the letter ā as \X2\0101\X0\. A room name loses its macron when an exporter skips that step. The facilities team then inherits the stripped name in its asset list.
New roads and public buildings in Auckland take Māori names with macrons. The New Zealand Gazetteer gives the official spelling of a place name. Our Reo Māori Localisation Services check road and facility names on drawing sheets and in model exports. We list the names found and the spelling corrected.
A Highway Section, Survey to Defects Period
The Asian Development Bank approved the Sustainable Highlands Highway Investment Program for Papua New Guinea in 2017. The road links Nadzab near Lae with Kagamuga near Mount Hagen. A survey team pegs the road reserve ahead of the works. Clans along the reserve point out gardens, graves and trade stores.
A resettlement plan lists the gardens and houses on the widened reserve. The Department of Works in Port Moresby pays compensation for crops against the schedule of the Valuer-General. A grievance committee hears disputed counts at the roadside. Our Tok Pisin Localisation Services write the compensation notices and the radio announcements.
The contractor lays the base course and seals the surface. A quality plan records compaction tests and bitumen temperatures. Traffic controllers stop public motor vehicles at the work zone. Their signals and the wording of the signs come from the traffic management plan.
The Defects Notification Period begins at taking-over and commonly lasts 365 days. The engineer lists defects in a notice and the contractor repairs them. From then the road authority maintains the section from a routine maintenance manual. A provincial works crew reads the manual with its drawings beside it.
Wind Loads under AS/NZS 1170.2
The standard AS/NZS 1170.2 sets wind actions for structural design in Australia and New Zealand. The current edition dates from 2021. Building codes in Fiji and Sāmoa refer designers to it. The works ministry in Apia checks permit drawings against the code. Our Samoan Translation Services translate home building guides and roof tie-down details for builders.
Engineers in Papeʻete work from French standards published by AFNOR. A lender or an insurer abroad asks for the calculation note in English. Our French Translation Services translate structural calculation notes and inspection reports. A structural engineer reviews the units and the load cases.
Guam builds to the International Building Code and to ASCE 7 for wind. A developer from Seoul building a hotel there submits structural calculations to the Department of Public Works in English. The design team writes its internal checks in Korean. Our Korean Translation Services translate design basis reports and review comments.
Nearby Work
Trades schools and church building committees use the site vocabulary above.
Trades Training
The Australia Pacific Training Coalition teaches construction trades from its head office in Suva. Trainers ask for assessment tasks explained in the language of the workshop, with tool and material names left in English.
Church Halls
A congregation in Wellington building a hall applies for a building consent under the Building Act 2004. The building committee reads the consent conditions in Samoan and answers the council in English.
Seawall Notices
A contractor placing rock armour on a shore near Tarawa posts tide and haulage notices for the village. We write the notice from the construction programme and record the dates agreed with the island council.